Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
Week of March 20

MEP:
  • SPK - sprinkler heads, testing on 2nd-3rd floors
  • Mechanical - controls, installing air outlets, cassette trims, cassette controls, FTR
  • Plumbing - installing sinks and faucets
  • Electrical - ground floor fixtures, light fixture in ceiling grid, installing and testing fire alarm components throughout, theater wire pulls
  • Low voltage - installing IDF room racks, terminating devices
Masonry - stucco in lightwells, removing scaffold
Drywall - 5th floor ceilings, 2nd & 3rd floor sheetrock and grid work, ceiling tiles on upper floors, taping throughout, stair soffits
Flooring - carpeting upper floors/hallways
Painting - priming throughout, topcoats throughout, painting stairs
Misc Metal - delivery and installation of stair rails, completion grease traps
Roofing - roof membrane and flashings, installing roof pavers, all roof levels
Millwork - installing of lab casework, tops and sinks, installing FT covers & general millwork
Stonework - tile in labs (walls), ground floor floor tile
Landscaping - roof metal edging work, soil delivery
Sitework - sewer work on 97th Street

Exterior Walls
  • north wall: panel work on east side, 5th floor terrace portal
  • ground floor: metal trim work

Saturday, March 25 (9:00 a.m. - 5:00 p.m.): continuation of scope above



Week of March 27

MEP:
  • SPK - sprinkler heads, testing throughout for fire alarms
  • Mechanical - controls, installing air outlets, cassette trims, cassette controls, FTR
  • Plumbing - installing sinks and faucets
  • Electrical - ground floor fixtures, light fixture in ceiling grid, installing and testing fire alarm components throughout, theater wire pulls
  • Low voltage - installing IDF room racks, terminating devices
Masonry - removing scaffold, completion of stucco/EIFS
Drywall - 5th floor ceilings, 2nd & 3rd floor sheetrock and grid work, ceiling tiles on upper floors, taping throughout, stair soffits
Flooring - carpeting upper floors/hallways
Painting - priming throughout, topcoats throughout, painting stairs
Misc Metal - installation of stair rails
Roofing - roof membrane and flashings, installing roof pavers, all roof levels
Millwork - installing of lab casework, tops and sinks, installing FT covers & general millwork
Stonework - tile in labs (walls), ground floor floor/wall tile, countertops
Landscaping - soil and irrigation work
Sitework - prep for exterior work

Exterior Walls
  • completion south first dloor
  • lounge area

Saturday, April 1 (9:00 a.m. - 5:00 p.m.): continuation of scope above




New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.



We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.