Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
Crane Use Notice: Please be advised starting the week of May 3, 2021, the superstructure work will require mobile crane use 2 to 3 days a week, weather permitting, on both 97th street and 98th street. In accordance with the approved DOT regulations, on crane days the roadway will be closed from 9AM to 5PM, Monday to Friday, and 9AM to 4PM on Saturday. Our subcontractor will post the requisite signage alerting the neighbors of the street closures. Please note this superstructure phase is though October 2021. 


Week of September 13

Casino

  • Shoring, formwork, and reinforcing for 6th floor slab
  • Pour 6th floor north side
  • Material deliveries for superstructure work, using knuckle boom/mobile crane. Concrete operations using concrete pump
  • Projected street closures: TBD
MEP rough in work on decks, hangers and supports in the cellars
S&E - installation/testing of interior hoist
Brick repairs at 114 East 98th Street
JJM - mobilize and start CMU on 2nd Floor

Saturday, September 18 (9:00 a.m. - 5:00 p.m.): continuation of scope above. Note: crane operation will be utilized. Lifting operation will commence at 10:00 a.m., as required by NYC; when loads are lifted, air horns are used to notify workforce. These are short quick blows of the air horn.


Week of September 20

Casino

  • Continue reinforcing for 6th floor south
  • Pour 6th floor south
  • Shoring, formwork, reinforcing for 7th floor slab
  • Material deliveries for superstructure work, using knuckle boom/mobile crane. Concrete operations using concrete pump
  • Projected street closure on 97th Street: TBD
MEP rough in work on decks
Brick repairs at 114 East 98th Street
JJM - continue CMU on 2nd Floor

Saturday, September 25 (9:00 a.m. - 5:00 p.m.): continue with reinforcing work on 6th floor slab



New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.



We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.