Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
To our neighbors: We are aware that a few construction workers have chosen to smoke on the sidewalks adjacent to the site. Unfortunately, smoking on the sidewalk is not illegal in New York City. We have nonetheless contacted the contractor to ask them to address the situation. We also asked them to review compliance with proper social distancing. 


Week of January 18
Excavation; rock chopping; waterproofing; south ejector pits; passenger elevator mat; equipment delivery

Saturday, January 23 (9:00 a.m. - 5:00 p.m.): install rebar and formwork, install waterproofing. No use of heavy equipment - only quiet work to be performed.


Week of January 25
Waterproofing; foundation wall gridline B; south ejector pits; passenger elevator mat; equipment delivery; minor rock chopping

Saturday, January 30 (9:00 a.m. - 5:00 p.m.): install rebar and formwork, install waterproofing. No use of heavy equipment - only quiet work to be performed.


New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.

Rock chipping should be completed by the end of January if all goes according to plan. We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.