Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
Crane Use Notice: Please be advised starting the week of May 3, 2021, the superstructure work will require mobile crane use 2 to 3 days a week, weather permitting, on both 97th street and 98th street. In accordance with the approved DOT regulations, on crane days the roadway will be closed from 9AM to 5PM, Monday to Friday, and 9AM to 4PM on Saturday. Our subcontractor will post the requisite signage alerting the neighbors of the street closures. Please note this superstructure phase is though October 2021. 


Week of May 23

MEP:
  • SPK - fire pump work, 3rd and 4th floor rough
  • Mechanical - 10th floor boiler room work, 5th floor mezzanine and kitchen, 3rd floor sheetmetal (theater)
  • Plumbing - 3rd and 4th floor rough
  • Electrical - generator room fit out, ATS, 2nd to 4th floor box/bx rough
Masonry - emseal work at south wall, 2nd floor CMU
Drywall - sheetrocking walls in sub cellars (gym), taping in cellar, core stair sheetrock, ongoing door deliveries, framing on floors 2-7, start sheetrocking on 3

Exterior Walls
  • north wall: layout and sub framing, 3rd-5th floors
  • east wall:  off hanging rigs - insulation and installing metal panels
  • west wall: off hanging rigs - framing clips and insulation, install metal panels
  • south wall: terracotta and trim on 2-4, sub framing 6-8
Windows - install windows up to 10, including caulking
Elevators - SE rails installation, PE machine room work

Saturday, May 28 (9:00 a.m. - 5:00 p.m.): continuation of scope or work above 


Week of May 30

MEP:
  • SPK - fire pump work, 3rd and 4th floor rough
  • Mechanical - 5th floor mezzanine and kitchen, 3rd floor sheetmetal (theater)
  • Plumbing - 3rd and 4th floor rough
  • Electrical - generator room fit out, ATS, 2nd to 4th floor box/bx rough
Masonry - 2nd and 3rd floor CMU
Drywall - sheetrocking walls in sub cellars (gym), taping in cellar, core stair sheetrock, ongoing door deliveries, framing on floors 2-8, sheetrocking on 3 and 4

Exterior Walls
  • north wall: layout and sub framing, 3rd-5th floors
  • east wall:  off hanging rigs - insulation and installing metal panels
  • west wall: off hanging rigs - framing clips and insulation, install metal panels
  • south wall: terracotta and trim on 2-4, sub framing 6-8
Windows - caulking windows up to 10, install window protection
Elevators - SE rails installation, PE machine room work

Saturday, June 4 (9:00 a.m. - 5:00 p.m.): continuation of scope or work above 

On Saturday, June 4, and Sunday, June 5, the rigging of rooftop mechanical units will require full roadway closures on 97th and 98th Streets. One street will be closed each day, but the order has yet to be determined. All work is weather permitting. 


New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.



We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.