Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
Week of August 15

MEP:
  • SPK - ground floor sprinkler rough in
  • Mechanical - cellar AHU piping, boiler flue installs, installing FTR
  • Plumbing - 7th-9th floor roughing, gas piping work, boiler room gas connections
  • Electrical - 8th & 9th floor box/bx rough, cooling tower power, 3rd floor generator room
  • Low voltage - cellar rough in wiring
Masonry - bulkhead stucco
Drywall - sheetrock on 6 and 7, taping stairways (5th & 6th floors)
Elevators - installing cabs for PE cars, SE hoistway work
Tile - WP and tile work on the 5th floor

Exterior Walls
  • north wall: installing terracotta
  • east & west walls:  off hanging rigs - gutter installation, metal panels

Saturday, August 20 (9:00 a.m. - 5:00 p.m.): continuation of scope or work above 


Week of August 22

MEP:
  • SPK - ground floor sprinkler rough in
  • Mechanical - cellar AHU piping, boiler flue installs, installing FTR
  • Plumbing - 7th-9th floor roughing, gas piping work, boiler room gas connections
  • Electrical - 8th & 9th floor box/bx rough, cooling tower power, 3rd floor generator room
  • Low voltage - cellar rough in wiring
Masonry - bulkhead stucco
Drywall - sheetrock on 6 & 7, taping stairways (5th & 6th floors), framing on 8th floor 
Elevators - installing cabs for PE cars, SE hoistway work, cab install
Tile - WP and tile work on the 5th floor

Exterior Walls
  • north wall: installing terracotta
  • east & west walls:  off hanging rigs - gutter installation, bottom panels

Saturday, August 27 (9:00 a.m. - 5:00 p.m.): continuation of scope or work above 




New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.



We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.