Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
To Our Neighbors: We are happy to report that the major rock chopping phase of our construction project has now been completed. We know how disruptive and difficult this phase of construction has been, and we greatly appreciate your patience and understanding over the last few months. Minor rock trimming may occur over the next two weeks, using a smaller machine, which will be less constant and less noisy. Thank you again for your continued support.

Week of March 8
  • Complete concrete pours at east foundation wall; concrete operations at west foundation wall; equipment and materials delivery; minor rock trimming for material installation (waterproofing, formwork).
  • Adjacent building protection @ 114 East 98 Street (in progress): sidewalk shed protection, roof protection, window (netting) protection.
  • Adjacent building protection @ 105 East 97 Street (tentative): sidewalk shed protection, roof protection, window (netting) protection. 

Saturday, March 13 (9:00 a.m. - 5:00 p.m.): install rebar and formwork; install waterproofing. No use of heavy equipment -- only quiet work to be performed.


Week of March 15
  • Complete concrete pours at west foundation wall (including pile caps and grade beam); concrete operations at PE 1-3 core walls; equipment and materials delivery; minor rock trimming for material installation (waterproofing, formwork).
  • Adjacent building protection @ 105 East 97 Street and 119 East 97 Street: sidewalk shed protection, roof protection, window (netting) protection.

Saturday, March 20 (9:00 a.m. - 5:00 p.m.): install rebar and formwork, install waterproofing. No use of heavy equipment - only quiet work to be performed.


New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.



We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.