Construction Updates
The NYC Department of Buildings (DOB) issued updated guidance on essential and non-essential construcion on April 15. Public and private school construction projects are now deemed essential, and Marymount's building project was confirmed as essential by the DOB on April 23. To facilitate the start of work under the current guidelines, contractors will follow safety protocols for social distancing onsite, augmented PPE, additional cleaning of surfaces, etc.

Inquiries:

646-218-8119
construction@marymountnyc.org
Crane Use Notice: Please be advised starting the week of May 3, 2021, the superstructure work will require mobile crane use 2 to 3 days a week, weather permitting, on both 97th street and 98th street. In accordance with the approved DOT regulations, on crane days the roadway will be closed from 9AM to 5PM, Monday to Friday, and 9AM to 4PM on Saturday. Our subcontractor will post the requisite signage alerting the neighbors of the street closures. Please note this superstructure phase is though October 2021. 


Week of January 10

Casino

  • Formwork and rebar for theater seating
  • Miscellaneous punch list and remedial work
  • Load out materials and equipment
MEP - ductwork and piping on cellar levels and through 8th floor, plumbing roof drains on 10th floor
JJM - ground floor CMU 
Anfield - drywall framing in cellar levels, rocking one side, framing at exterior walls and stairs
STNY - mobilize site, set up shanty layout
PGNY
  • exterior wall framing, 4th to 8th floors
  • densboard and WP, 2nd to 5th floors, south wall
  • mobilizing and erecting hanging rigs, east wall
Saturday, January 15 (9:00 a.m. - 5:00 p.m.): continuation of scope of work above 

Week of January 17

Casino

  • Prep for theater seating pour
  • Miscellaneous punch list and remedial work
  • Load out materials and equipment
MEP - ductwork and piping on cellar levels through the 8th floor, plumbing roof drains on 10th floor
JJM - continue CMU on ground floor, fill ins in cellar
Anfield - drywall framing in cellar levels, rocking one side, framing exterior walls and stairs
PGNY - exterior wall framing, 4th to 8th floor, densboard sheeting on north side, WP
STNY - taking deliveries and commence receptors

Saturday, January 22 (9:00 a.m. - 5:00 p.m.): continuation of scope or work above 



New York Department of Building standard work hours are Monday through Friday from 7:00 a.m. to 6:00 p.m. Exact timing of construction schedule is dependent upon weather conditions and may be subject to change.



We hope to keep to this expected schedule but will keep you updated if there are any unexpected delays in our plans. Check back to this page for detailed updates on the construction timeline as they become available.